The Q & A’s.

Select the + icon in order to view the answers.

First, supporting brickwork has to be built up to the slab’s soffit level. Then we install temporary propping to support the deck. Props are placed between 1.2m and 1.5m apart, and are all connected by ledgers. This will give us a secure structure to build the deck on.

After the props are erected, we start to build the deck. The deck mostly consists of steel decking panels / shutters, and this will hold the wet concrete in place while it is curing.

On top of the deck, we then install a mat of steel reinforcing bars. The spacing and diameter of the reinforcing is calculated by a structural engineer, and differs on every project due to various factors. This is such an important part of concrete slabs that the engineer has to inspect and approve the reinforcing after it is installed, before any concrete is cast.

After the reinforcing is in place, the plumber and electrician has an opportunity to install pipes and conduits that will be cast inside the slab. This eliminates the need for ceilings under the slab, and helps reduce the construction costs.

When everything is in place, and the engineer has approved the reinforcing, it is time to place the concrete. Concrete consists of specific quantities of small stones, sand, cement and water, depending on the required strength. Ready-mix concrete is mixed at a batch plant near the site and is delivered to site in concrete mixers mounted on trucks. The plant has precise mixing recipes than ensures the final strength much more accurately that conventional mixing, and it’s all done much faster than as well.

On most sites, the level at which the concrete is discharged from the mixer trucks will be lower than the deck. When this is the case, the concrete has to be pumped to where it is needed.

The concrete will be placed on the deck with exact thicknesses that was also calculated by the engineer. The top surface of the concrete is normally levelled to a rough finish, which is ready for the main contractor to apply a screed before the final floor covering (such as tiles or carpet) is added.

The top surface can also be powerfloated, which will give it a very smooth finish. This is generally done in areas that will have exposed concrete with no other floor finish, such as in garages or where the client prefer to have an exposed concrete finish.

One to two weeks after the slab has been cast, the propping and the deck is all removed, and the slab will remain in place, supported on the walls underneath it.

We do all types of formwork for all types of concrete structures, such as columns, beams, staircases, ground beams, raft foundations and surface beds. Please feel free to contact any of our consultants for assistance or queries regarding this.

This obviously greatly depends on the size of the slab. Other factors that can influence the construction time are the shape of the slab (rounded edges takes longer than straight edges); the amount of beams (if required); and the site location and access. On a small to average size slab, the propping and deck will generally take three or four days, the reinforcing a day or two, and then the engineers inspection, electrical and plumbing will generally happen in the following day or two. This means most slabs will be ready to pour within a week to ten days from starting with the project. However: all projects differ, and we recommend you consult your agent about an estimated construction time when a quotation is issued.

The props has to remain in place until the slab can support its own weight. Concrete curing times may vary and will be influenced by the amount of water in the concrete, the strength required, and weather conditions, such as continues rain or extremely hot or cold conditions. Generally the temporary support will be removed 7 to 14 days after the concrete is cast, but this can be increased by the structural engineer if the design requires.

Although we are based in Gauteng, we have hubs covering most of Southern Africa. Feel free to contact one of our consultants if you are unsure about your area.

This depends on how many projects we are busy with at the time, and can vary from a couple of days up to as long as six weeks. Thus we recommend you start getting quotations and appointing us as soon as you start with construction. Also, having an engineer appointed from the start of the project could save thousands by optimizing the layout to save costs on the slab, as well as prevent having to break down parts of walls to accommodate the slab.

We have a team of engineers that will design and inspect the slab and supply an engineer’s certificate. The engineer will design the structure to be safe, but also at the lowest construction cost. All municipalities/councils require an engineer to oversee all projects. It is thus ideal to have one engineer to assist with the entire project to design all structural components, from the foundations to the slab. This is why more and more owners appoint an independent engineer themselves, or involve the slab contractor early in the project to benefit from the engineer’s assistance. If you already have an engineer appointed, the engineer’s cost will not be included in your quotation, so please advise your consultant in advance.

We require all supporting brickwork to be level and built up to the slab’s soffit level, so the client will probably require a bricklayer. If the project involves electrical work and plumbing, as most projects do, the client will also need to appoint these specialists. As explained above, pipes and electrical conduit can be hidden inside the slab, if they are in place before concrete is cast, so it is ideal to have these specialists appointed early in the project.

Due to our construction method, the slab soffit will not have a perfectly smooth finish. If the client prefer, it can be plastered and painted. The top surface may also be screeded, as stated above. Curing of the concrete is a very easy process, but is very important, and is also the responsibility of the client. This can all probably be done by the bricklayer/main contractor. Roof slabs and open balconies may require to be waterproofed. This should be done by a specialist. Because of the extent of these items, many owners that aren’t familiar with the construction process decide to appoint an experienced main contractor to handle all these items.

The factor that mostly influence the cost of a slab, is the floor layout. The slab thickness can be reduced and the need for beams can be eliminated by limiting the distance between loadbearing walls on the ground floor. Large open spaces without supporting walls will increase the slab thickness, and large openings in walls, such as for double garage doors, may require beams. All of these increase costs. Ask your architect or draftsman to contact any of our consultants for more information or assistance.

The cost of the slab can vary from R600/m² to R1200/m² or more, depending on the design, the size of the slab, and distance from any of yards. The only way we can give an accurate quotation, is to do a preliminary design of the slab and to price it accordingly. To do this, we will require a copy of the architects’ drawings. We do quotations free of charge, and they normally are ready within a day or two.

Drawings can be sent to info@firstfloorslabs.co.za or you can Whatsapp them to 072 490 3957. If you are unable to send the drawings to either of these contacts, please contact one of our consultants for assistance.

Don’t give up hope, we can still assist you. We could send someone to take measurements on site. Please contact one of our consultants for assistance.

When building on top of an existing ground floor, it is important to check that the existing walls will be able to carry the extra weight. This includes the foundations, and depending on the circumstances, the engineer may require an inspection of the existing foundations or additional support may be required. One of our consultants should be able to assist you with this.

Keep in mind that erecting a slab involves wet concrete and heavy equipment, and although we take great care to protect existing finishes, we cannot guarantee this. The best is to remove items such as built in cupboards and other fittings, before any work starts. Some floor finishes may also need to be replaced after the slab is finished.

Extending a building outside its existing footprint is a much easier process. Slabs can easily be joined to existing structures, and it can then be done before any finishes are installed, preventing the risk of damaging them. When requesting your quotation, please inform your consultant if any parts of the building are existing.

Send us your enquiry.

Thank you for your message. It has been sent.
There was an error trying to send your message. Please try again later.